Sector | Project Name | Project Location | Contract Sum | Amount Paid | Status % |
---|---|---|---|---|---|
Water Services | Water & sanitation grant | Kwale HQ | 338,611,223 | 325,417,009 | 96% |
Water Services | Pipeline Ext Nyalani/Mwangoni/Banga.Vigurungani/TTC | Puma ward | 159,325,618 | 159,325,618 | 100% |
Executive Services | Governors Residence | Tsimba/Golini | 183,403,077 | 124,007,035 | 0.68% |
County Assembly | External works on Assembly Complex | Tsimba/Golini ward | 156,399,413 | 119,716,751 | 77% |
County assembly | Assembly Complex Fittings/Fixtures | Tsimba/Golini | 136,525,897 | 110,800,717 | 81% |
Social Services | Const Kwale Stadium | Kwale | 102,429,001 | 85,866,697 | 84% |
Trade | Const of Fruit Processing Plant | Shimba Hills | 67,794,770 | 69,894,770 | 90% |
County Assembly | Assembly Complex/Mechanical works | Tsimba/Golini | 69,486,668 | 55,730,344 | 80% |
Trade | Diani market | Ukunda | 46,730,483 | 46,730,483 | 100% |
Education | Completion of Kwale TTC | Puma | 46,091,843 | 46,052,094 | 99.9% |
Sector | Project Name | Project Location | Contract Sum | Amount Paid | Status % |
---|